Full MEP design including coordination and O&M Manuals for Contractor. The design works included;
Mechanical – new 4-pipe fan coils from CHW, LTHW and condensate pipework distribution, primary fresh air mechanical ductwork to the rear of the fan coils with extract bell mouths at the riser cores. New toilet extract and supply to the core areas.
Electrical – New LV power distribution from landlord rising busbars to local distribution boards serving underfloor powertrac installation for future fit out. New lighting design to suit the requirements of the office. Design and coordination of specialist packages including fire alarm and security.
Public Health – New hot and cold water installation to service the core area toilets and the future provision to serve tenant fit out areas from the riser.